The John Street Roadwork Project is advancing as planned. Work has progressed as follows:
- Milling was completed on Friday 4/30/21.
- Crack sealing started on Monday 5/3/21.
- Full depth asphalt repairs of localized deteriorated areas started on Monday 5/3/21.
Final Paving will begin once full depth areas are completed. It is anticipated that paving will begin next week.